News & Reviews News Wire Amtrak Inspector General seeks risks of cost overruns, delays in Baltimore tunnel project

Amtrak Inspector General seeks risks of cost overruns, delays in Baltimore tunnel project

By Trains Staff | October 2, 2024

Report says company has not fully completed needed planning for Frederick Douglass Tunnel project as start of construction approaches

Email Newsletter

Get the newest photos, videos, stories, and more from Trains.com brands. Sign-up for email today!

Map showing route of the current B&P Tunnel and the planned route of the Frederick Douglass Tunnel which will replace it.
The planned route of Baltimore’s Frederick Douglass Tunnel (in green). In a new report, the Amtrak Office of Inspector General raises concerns about planning as the project prepares to begin construction. Amtrak

WASHINGTON — Amtrak is increasing the risk of cost overruns and schedule delays on Baltimore’s Frederick Douglass Tunnel project because it has not completed all necessary planning as the start of major construction approaches, the Amtrak Office of Inspector General says in a report released Tuesday, Oct. 1.

Major construction is slated to begin this year on the $6 billion project to replace the B&P Tunnel, which dates to 1873 and is a major bottleneck on the Northeast Corridor because of 30-mph speed restrictions and increasing repair needs. Amtrak selected the builder for the new 1.4-mile tunnel in February, and selected two major infrastructure firms to manage the project in April [see “Amtrak chooses joint AECOM/Jacobs venture …,” Trains News Wire, April 3, 2024].

Responsibility for the tunnel project was given in 2022 to Amtrak’s new Capital Delivery department, which initially assigned it to a single individual. By October 2023, the program team had grown to seven members, but five of six staff-level members told Inspector General auditors that they were overwhelmed by the workload. Amtrak officials acknowledged staffing was insufficient, in part because of funding restrictions, and said the Capital Delivery team should have been staffed before it received responsibility for the program.

The Inspector General report also says Amtrak did not establish a program management structure early enough, and as a result struggled to complete the necessary planning in scheduling, communications, document management, and risk management. Delays resulted and the risk of cost overruns and additional delays has increased as a result. And the firms managing the project must complete management planning at the same time construction preparations begin.

The report makes three recommendations: That it complete program management planning for the tunnel project; that it establish processes to ensure a project’s management structure is established early enough to produce strong oversight for the life of the project; and that it establish processes to ensure program teams have sufficient staff before projects are assigned to the Capital Delivery department. Amtrak, in its response to the report, says its management agrees with the recommendations and outlined how it acting to meet those goals.

The full report, including Amtrak’s response, is available here.

7 thoughts on “Amtrak Inspector General seeks risks of cost overruns, delays in Baltimore tunnel project

  1. Had the opportunity to take a NEC RT last weekend between DC and Phila. 30th St, thus thru the B&P tunnel both ways. Aside from stretches of bad track/slow orders, bridges were also bottlenecks. Worse than my first Metroliner ride in Fall 1972. Time to pay the piper.

    1. Curtis, do you happen to recall the announced completion date for the new tunnels if all goes well and per plan?

    2. Without delays, the new Frederick Douglas Tunnel will be completed in 2035 — per AMTRAK.

You must login to submit a comment