By Trains Staff | October 7, 2024

Ruling overturns lower-court decision that said government had failed to consider health impacts of Milton Logistics Hub

Email Newsletter

Get the newest photos, videos, stories, and more from Trains.com brands. Sign-up for email today!

Rendering of proposed rail yard
An illustration shows Canadian National’s planned Milton, Ont., intermodal terminal. An appeals court ruling will allow the project to move forward. Canadian National

OTTAWA, Ontario — Canada’s Federal Court of Appeals has overturned a lower-court ruling blocking Canadian National Railway’s development of a Toronto-area intermodal facility, allowing construction of the terminal to move forward.

The Canadian Press reports that a three-judge panel ruled on Friday that the federal government’s decision to allow construction of the facility in Milton, Ontario, was reasonable despite “significant adverse environmental effects.” That overturned a March decision that found the government had failed to consider the adverse impact of diesel exhaust from locomotives and trucks at the Milton Logistics Hub [see “Court blocks CN plans …,” Trains News Wire, March 5, 2024]. The appeals court had previously stayed the lower-court decision while it considered CN’s appeal, allowing construction to continue [see “Canadian court allows work to continue …,” News Wire, May 13, 2024].

The government had previously approved the CN project after attaching 325 conditions regarding environmental protections, but the Halton Region and its four municipalities challenged that decision, saying the project put the health of residents at risk. The appeals court found that the government had acted after giving due consideration to human health.

Halton Region spokeswoman Lindsay Di Tomasso said the region was considering its legal options and is “deeply concerned” that the project has been approved.

The Milton site is about 25 miles southwest of downtown Toronto. CN has called the facility “a critical piece of infrastructure” because other intermodal terminals in the region are operating at capacity.

One thought on “Canadian appeals court gives CN Toronto-area intermodal facility the go-ahead

  1. I’m certainly no “greenie” but there’s an important point here. Transitioning between modes has a huge environmental impact. Whether it’s a container port in Long Beach, or an airport, or rail-truck intermodal yard. On the rail side, the environmental impact of a container yard must rival the environmental impact of the train hauling the container across a continent. On the truck side, all the drayage on the Interstate has to start or end somewhere.

    You can marvel at the efficiency of a 15,000 foot stack train making its way across Wisconsin. What happens when that train reaches its destination near Chicago?