The new Mustang flux pellets will replace the Viceroy taconite pellets previously produced at its recently shuttered Empire Mine near Marquette, Mich. The Empire Mine, also served by CN, came to the end of its natural life in 2016. The Empire mine has been operating since 1963.
The “Mustang” pellet is specially formulated for ArcelorMittal. The “flux” pellet uses a limestone binder during its production. CN also brings limestone from Hallett Dock in Duluth to the plant to produce the Mustang pellets, adding more carloads.
Cliffs invested a total of $75 million in cash to build a new storage facility, silos, and a limestone crusher, conveyors, and rail infrastructure to support production of the Mustang pellet. The company broke ground for the project at a ceremony in August 2016. Construction jobs created for the Mustang project included 120 people employed at peak construction. About 40 percent of United Taconite’s production will be geared to Mustang, while about 60 percent will be geared to its standard pellet output.
Cliffs will host a ribbon-cutting event for the new facility at United Taconite May 30.
Is the spruce tree on the front porch of unit 6253 in the article photo just a festive decoration for the first taconite train?
Too bad it’s not an all-rail route! I miss the ore trains down here in southeastern Wisconsin.
Yes, the tree is traditional for the first loads out of a mine.