News & Reviews News Wire Union Pacific, Norfolk Southern offer first look at 2019 capital plans NEWSWIRE

Union Pacific, Norfolk Southern offer first look at 2019 capital plans NEWSWIRE

By David Lassen | January 7, 2019

| Last updated on November 3, 2020

Get a weekly roundup of the industry news you need.

Email Newsletter

Get the newest photos, videos, stories, and more from Trains.com brands. Sign-up for email today!

UP_RiverForest_09092018_Lassen
A Union Pacific train threads its way through construction at Vale, in River Forest, Ill., where the railroad is building a 1.8-mile section of third track.
David Lassen
MARCO ISLAND, Fla. – One of the annual limitations of the early January date for the the National Railroad Construction and Maintenance Association Conference is that most railroads are not yet ready to announce all details of their capital spending plans, particularly their dollar commitments. This was the case on Monday, as Union Pacific and Norfolk Southern provided overviews of their capital plans for 2019. Still, there are trends to note from the two railroads’ presentations.

Union Pacific offered no comparison to its 2018 capital figure of $3.3 billion, but the presentation by Eric Gehringer, vice president of engineering, showed a continuing focus on addressing needs in Texas and Louisiana.

That includes the company’s largest-ever capital project, the $550-million Brazos hump yard near Hearne, Texas. “There is a tremendous amount of focus and pressure to ensure that this yard is built no later than Christmas of this year,” he said. “And we are on schedule, due to the hard work of a lot of people.”

Brazos is a massive undertaking, with 64 miles of track. The bowl track, in its entirety, could hold an 18-mile-long train, Gehringer said. Construction has involved moving 2.8 million cubic yards of dirt, and 206,000 linear feet of drainage.

The yard is the largest piece of the railroad’s efforts to increase capacity, which mostly will fall in three areas, Gehringer said: yard extensions and expansions, new sidings, and siding extensions. Those projects are “spread across the entire system, but the preponderance is down in that Houston-Louisiana area.”

UP’s maintenance plans for 2019 include replacement of 3.7 million ties, 515 miles of rail, and 170 miles of ballast renewal. And the company is trying to reduce the maintenance windows required for that work, an effort receving even more attention under the Unified Plan 2020, UP’s version of Precision Scheduled Railroading.

“You’ll see us combine gangs that haven’t historically worked together,” he said. “… The plan we have now, if you compare it to [2018], we’re putting in about the same amount of units across the board, but we’re doing it with 20 percent less curfew time. That’s a huge number. A world-class improvement would be 3 to 6 percent.”

New technology will help that effort. In less than three months, the company will receive its first new machine designed to streamline tie-plate distribution during the rail-laying process. It will reduce the number of times a plate is handled during the process from 11 to two.

For Norfolk Southern, project spending for 2019 will be roughly equal to 2018, said Jon Zillioux, associate vice president of sourcing. NS’s capital spending in 2018 was $1.8 billion.

The railroad is planning some 72 projects this year. Capacity projects, in the form of new or extended sidings, will allow the sidings to handle trains up to 14,000 feet. NS will also be expand intermodal facilities at two Chicago sites, as well as facilities in Sharonville, Ohio; Rossville, Tenn.; Kansas City, Mo; and Austell, Ga. Major building projects a new car shop in Buffalo, N.Y.; a crew building at Moorman Yard in Bellevue, Ohio; and operations buildings in Pitcairn, Pa., and Northumberland, Pa.

The NS maintenance plan for 2019 include replacing 99,179 tons of welded rail, 252.8 miles of dual rail and 162 miles of single rail; 2.5 million ties; 2.1 million tons of ballast; and 70 bridge and 100 culvert rehab and replacement projects, ranging in cost from $100,000 to $4 million.

Outside of the normal engineering projects, NS is also beginning work on its recently announced move to a new headquarters in Atlanta. “In fact,” Zillioux said, “the [request for proposals] is going out tomorrow for interior work.

“What the company’s trying to accomplish is to approve our alignment,” Zillioux said. “It would be much nicer for our group, for example, to be where our operating folks are. We’re not. They’re in Atlanta; we’re in Norfolk. It’s one thing to email or talk on the phone, but it’s much better to walk down the hall and talk to those folks.

“Well, you can expand that out to our marketing and operations groups, which are also separate. They need to be joined at the hip. They work very well together, but you can’t take away from actually being closer together.”
Trains News Wire will be posting regular coverage for the duration of the conference.

6 thoughts on “Union Pacific, Norfolk Southern offer first look at 2019 capital plans NEWSWIRE

  1. UP’s Gehringer’s comments about reducing maintenance of way windows is a significant item. It’s common sense but difficult to achieve with the variety of trackwork necessary – rail, tie and curve gangs, ballast, surfacing, bridgework, et al. So relatively intensive maintenance on medium-high density corridors takes a bite out of effective capacity during maintenance windows. Work has been concentrated over the years whenever possible, however, a system-wide focus on maximizing capacity should pay big results in over-the -road performance.

  2. I knew Jon Zillioux when he worked in Atlanta. I worked in the Bridge Office and he was in Engineering Systems at that time.

  3. Interesting photograph (taken in my stomping grounds) accompanying this article. The telephoto lens has compressed the entire 1.8-mile project (and then some!) into the view. The bridges in the background are those for 25th Avenue and the IHB as they cross the UP main line. The new track starts out to the north of the existing two, but moves to the south in the vicinity of the Melrose Park Station; I assume all three main tracks will make a smooth jog to accommodate this.

    What’s hard to see is the new bridge span over the Des Plaines River, which is just this side of the first grade crossing (First Avenue) shown. The deck is almost completed as we speak.

    Still to come: a third track between Kress (west of West Chicago) and Peck (west of Geneva). That’s a distance of 6.1 miles (probably all to the south of the existing main line). So far, I’ve seen nothing to suggest that work is being done on this. The work will be more involved for this one, including the widening of one or more overpasses, and an additional span over the Fox River (if they’re lucky, the existing piers can be used).

  4. Union Pacific and Norfolk Southern are successors of the first two railways I travelled and grew up on: Missouri Pacific Railroad and Southern Railway, respectively. If there is another mega-rail merger these two railways would be best suited for each other. Of course, the combined company would be named Union Pacific for its more universal application and legend.

  5. Yes, I’m quite impressed. Especially in that today is the day I read on this website that each of the two railroads can’t get an Amtrak train through, not even (in UP’s case) one that runs triweekly.

You must login to submit a comment