News & Reviews News Wire Transport Canada orders CM&Q to repair rail line near Lac-Mégantic NEWSWIRE

Transport Canada orders CM&Q to repair rail line near Lac-Mégantic NEWSWIRE

By Angela Cotey | September 11, 2019

| Last updated on November 3, 2020

Get a weekly roundup of the industry news you need.

Email Newsletter

Get the newest photos, videos, stories, and more from Trains.com brands. Sign-up for email today!

CMQ9010
Central Maine & Quebec train No. 2 heads east near Long Pond, Maine, in November 2017.
Justin Franz
LAC-MÉGANTIC, Quebec – The Canadian government has ordered the Central Maine & Quebec Railway to make repairs to its rail line between Farnham and Lac-Mégantic after an inspection revealed numerous track issues.

CM&Q took over the rail line through Lac-Mégantic after previous owner Montreal, Maine & Atlantic Railway went bankrupt as a result of a devastating 2013 oil train accident. The derailment and subsequent explosion leveled 30 buildings and killed 47 people in the small lakeside community not far from the Maine border.

According to a press release from Transport Canada, an inspection in May found a number of deficiencies on the 125-mile route between Farnham and Lac-Mégantic, including defective rails and ties and muddy ballast. The railroad had also issued a number of slow orders on the route. The government ordered CM&Q to fix the issues immediately and since then the railroad has reported that it corrected more than 250 deficiencies.

On Sept. 6, Minister of Transport Marc Garneau issued a follow up order, forcing the CM&Q to conduct more track inspections along the route and maintain certain slow orders on the route until Transport Canada can do an independent inspection.

“Transport Canada officials will analyze the results of the inspections carried out by CMQR. In the coming days, they will also carry out on-site inspections to ensure that the corrective actions comply with railway safety standards and regulations, and inspect the 125-mile section of rail lines between Farnham and Lac-Mégantic,” Garneau says.

The press release issued by the government leaves little doubt as to why CM&Q’s maintenance program is being scrutinized.

“The tragedy of July 6, 2013 in Lac-Mégantic will forever remain in our collective memory. I would like to say once again that rail safety remains my top priority, and that I will continue to do everything within my authority to improve it,” Garneau says.

Trains News Wire is unable to reach CM&Q officials for comment. However, in past interviews, the railroad has touted the improvements it has made since taking over the railroad from MM&A.
For more on the Central Maine & Quebec, see the August 2019 issue.

2 thoughts on “Transport Canada orders CM&Q to repair rail line near Lac-Mégantic NEWSWIRE

  1. Just because the track is “better” doesn’t mean it’s acceptable.

    Can you really blame the people of the town for not wanting long oil trains rolling through after 50 of them died?

  2. This is very ironic, considering that 1 – track condition was not a factor in the Lac Mégantic tragedy and 2 – track condition is way better today than it ever was under Montreal Maine & Atlantic.

    Transports Canada trying to look good as a Federal election is under way, starting today, perhaps?
    Or just trying to put Central Maine & Quebec out of business and saving themselves the enormous cost of building a bypass around Lac Mégantic for a mere 10 trains a week?

You must login to submit a comment