“We continue to work directly with all ‘to be compliant’ railroads — providing technical support and guidance as requested — to enable them to satisfactorily meet the Congressional deadline,” FRA Administrator Ronald L. Batory said. “I’m pleased with the growing number of railroads that have reached critical milestones, and continue to encourage all of them to help each other overcome any remaining challenges from their respective lessons learned.”
As of March 31, 2020, PTC systems were in RSD or in operation on 56,541 route miles — 98% of the nearly 58,000 route miles subject to the mandate. Specifically, at the end of the first quarter of 2020, PTC systems were governing operations on all PTC-mandated main lines owned or controlled by Class I freight railroads and other freight host railroads subject to the mandate.
While most commuter railroads’ PTC systems are in RSD on their entire mandated networks, work remains, as 63.2% of all commuter railroads’ cumulative required route miles were PTC-governed as of March 31, an 8.5% increase since last quarter. In addition, interoperability has reportedly been achieved in 48.5% of the 229 applicable, host-tenant railroad relationships as of March 31, 2020, a 10% increase since the fourth quarter of 2019.
Recognizing that 33 weeks remain until the final implementation deadline set forth by Congress, FRA continues to direct additional staff resources to railroads at risk of not fully implementing an FRA-certified and interoperable PTC system on their required main lines by December 31, 2020. To evaluate the risk of non-compliance, FRA is primarily considering the following factors: (1) the percentage of mandated route miles currently governed by a PTC system, including RSD; (2) any unresolved technical issue in implementing a compliant PTC system; (3) the percentage of a host railroad’s tenant railroads that have achieved required interoperability; and (4) a host railroad’s expected date to submit its PTC Safety Plan to FRA, necessary to obtain PTC System Certification.
Based on railroads’ self-reported progress on these factors as of March 31, 2020, FRA currently considers the following four host railroads at risk of not fully implementing a PTC system on all required main lines by December 31, 2020: NJ Transit, TEXRail, Chicago’s Metra, and New Mexico Rail Runner Express (Rio Metro).
“We strongly urge the collaborating railroads to work in a safe, focused and aggressive manner to meet this end-of-year deadline,” Batory said. “FRA has provided nearly $2.6 billion in grants and loans and thousands of hours of technical assistance to help railroads fully implement PTC systems.”
FRA remains fully committed to facilitating railroad efforts to complete all remaining work. In addition, FRA is encouraging state departments of transportation and governors to help any at-risk commuter railroad within their states to ensure they have sufficient technical resources and support to meet the end-of-year deadline.
More information is available online.
— From a Federal Railroad Administration news release. May 15, 2020.
Or it could be that they are both in states where the most recent former governor’s refused to increase or dramatically decreased funding for moving the workforce in the most efficient way possible– one for 8 years. Additionally, the legislatures did not make public transit a higher priority and each state’s taxpayers admittedly are heavily taxed in relationship to other states– but they also get quite a bit for that