Trouble on the Transcon

By Bill Stephens | August 31, 2022

Issues on BNSF's Chicago-California route reflect railroads' struggles across the country with crew shortages

Email Newsletter

Get the newest photos, videos, stories, and more from Trains.com brands. Sign-up for email today!

BNSF Railway Long Beach, Calif.-Logistics Park Chicago international stack train S-LBELPC1 departs Barstow, Calif., on Aug. 9, 2022. Two westbound intermodal trains are awaiting crews at the yard, while three more westbound trains are holding outside the yard. (Bill Stephens)

Earlier this month, Trains drove alongside BNSF Railway’s Southern Transcon from Barstow, Calif., to Belen, N.M., to see how North America’s busiest freight railroad and intermodal corridor is faring amid the crew shortages that have affected operations. BNSF’s California and Southwest divisions have been among the hardest hit in the country as the big four U.S. Class I railroads aim to replenish train crew staffing levels. An in-depth feature on the impact of crew shortages will be published in an upcoming issue of Trains.


Amid crew shortages and a supply chain that has almost as many kinks as links, BNSF Railway’s Southern Transcon across the Southwest is two railroads wrapped up in one.

The first railroad you already know: It’s the intermodal artery that carries a fleet of priority Z-symbol hotshots and Q-symbol guaranteed-service stack trains. From trackside, they seem to be relatively immune to the railroad’s operational problems. While approaching Winslow, Ariz., on Interstate 40, you look across the sagebrush and glimpse eastbound and westbound intermodal trains rolling along at track speed, closing in on each other at a combined 140 mph. And crew changes are snappy, with fresh crews at the ready and highballing the trains out of town, often in 10 minutes or less.

The second railroad isn’t moving well — and sometimes isn’t moving at all. In old passing sidings from Barstow to Belen sit woebegone merchandise and international S-symbol stack trains. Some have been stripped of their locomotives and have been idle for days, or even a week or more. Lower-priority international intermodal, merchandise, and bulk trains also tend to congregate in and around terminals when rested crews are not available to take them on the next leg of their trips across the former Santa Fe main line.

The merchandise trains are tied down because scarce crews are being allocated to service-sensitive intermodal trains, a practice other railroads are following, too. BNSF’s unusual embargo on certain types of carload traffic bound for California, which began June 27 and will end Sept. 5, also plays a role as the railroad works off a backlog of traffic in Southern California.

The eastbound international stack trains, carrying containers imported through the ports of Los Angeles and Long Beach, are in a holding pattern. They’re awaiting space at clogged intermodal terminals in Chicago, Memphis, Kansas City, and Fort Worth.

Simply put, supply chain problems beyond BNSF’s control mean that volume is coming into the ports faster than cargo owners are picking up their freight at inland terminals. So those S-symbol trains – two dozen or more scattered between California and Chicago – are marooned until they are able to leapfrog closer to their destinations. As the No. 1 international intermodal carrier by volume, BNSF is far more affected by this phenomenon than the other railroads.

A thunderstorm threatens as BNSF Railway Q-LACLPC6 rolls east through West Defiance, N.M., on Aug. 11, 2022. (Bill Stephens)

Meanwhile, Mother Nature isn’t doing BNSF any favors. The monsoon season in the Southwest frequently brings the railroad to a temporary halt when high wind warnings and flash flood warnings are hoisted.

The congestion — related to crew shortages, supply chain problems, and bad weather — prompted a fourfold spike in recrews. At its peak in June, more than 20% of BNSF’s trains in California, Arizona, and New Mexico went dead on the federal 12 hours of service law and had to be tied down en route, chewing up more capacity and exacerbating crew shortages.

This is not BNSF’s finest hour. But it’s far from being alone in the doghouse with shippers and regulators. CSX Transportation, Norfolk Southern, and Union Pacific to varying degrees find themselves in the same fix. They’re short of train crews. And if you don’t have all the people you need, a railroad quickly coagulates.

BNSF Railway Q-STOCHI6 is among the trains running short on time as it rolls through Maine, Ariz., on Aug. 10, 2022. (Bill Stephens)

Caught short

When a foreman requests track time on BNSF’s Seligman Subdivision near Flagstaff, Ariz., the dispatcher quickly says he’ll have to wait. “I’ve got seven eastbounds coming at you, and they’re all short-timers,” she explains. Her goal: Make sure the trains arrive at Winslow without running afoul of the hours of service law.

Nowhere has been harder hit by recrews than BNSF in California and across the Southern Transcon in Arizona, New Mexico, and Texas. In this wide swath of territory, the percentage of trains requiring a recrew en route has consistently been the highest in the U.S. since May, according to a review of data reported to the Surface Transportation Board. BNSF’s extra boards in the Southwest are threadbare, leaving the railroad with little cushion to absorb the impact of frequent recrews.

How did BNSF get into such a jam?

The railroad says congestion in Southern California wasn’t a result of any one circumstance, but rather a culmination of multiple factors, including operational constraints, resource levels, and bad weather. Labor leaders say BNSF’s controversial Hi-Viz attendance policy was a factor, too, because it led some veteran crews to leave the railroad. BNSF disputes this and says Hi-Viz has improved crew availability.

BNSF Railway has been short of crews in Needles, Calif. (Bill Stephens)

Whatever the case, this much is clear: The epicenter of BNSF’s Southwest crew shortage has been Needles, Calif., an old Route 66 town on the Arizona border. As it goes, so goes the 179.6-mile Needles Subdivision to Barstow, the junction of BNSF’s main lines to the Los Angeles Basin and Northern California via the Central Valley.

“Barstow is by design a staging location to meter trains over the Cajon into the Basin and Tehachapi into The Valley, and the Needles Subdivision is a buffer to assist in facilitating optimal meeting times,” spokesman Ben Wilemon explains. “Early on we had a reduction of crews due to attrition. Many businesses in California encountered a similar situation as residents were relocating out of state to less expensive locations. It was difficult to balance employee needs as the volumes were coming in waves and were unpredictable.”

Needles, with a population of less than 5,000 people, is not an easy place to hire. The closest cities to recruit conductors from are Bullhead City, which has a competing job market with nearby casinos, and Lake Havasu City, which is a 45-minute drive to Needles.

A crewman climbs down from an eastbound intermodal train that has just arrived for a crew change at Needles, Calif., on Aug. 9, 2022. The train, Q-LACATG6, would roll out of town 10 minutes later. (Bill Stephens)

The active crew base at Needles is more than 470 train, yard, and engine employees. As of mid-August, BNSF had filled 34 of the 49 vacant positions, and another 25 people have accepted the railroad’s job offers. BNSF also had 36 crew members transfer temporarily to Needles from other areas on the system.

The new crews can’t pitch in right away. “The new additions to the territory must undergo four months of initial training followed by six months of territory training for familiarization,” Wilemon says.

Imbalanced traffic flows don’t help the crew situation as eastbound trains outnumber westbounds, leaving crews and locomotives out of position, particularly on the Needles Sub.

At the other end of the Southern Transcon, intermodal customers have been slow to pick up their containers at Chicago terminals, particularly Logistics Park Chicago, or LPC, amid high volume and a shortage of chassis, truck drivers, and warehouse capacity.

“Over-ordering earlier this year has left retailers with stagnant merchandise in their stores and crowded warehouse distribution centers with remaining storage space at 1-2%,” Wilemon says. “This has resulted in the usage of boxes on chassis as a storage solution where it’s far cheaper than the cost of storing a container at a marine terminal or rail facility. As a result, chassis cycle times are impacting the availability of those assets to unload trains, and consequently, we are having to meter volume at ports.”

Railroads have had to deal with the slow unloading problem since intermodal traffic rebounded from pandemic declines the second half of 2020. And on BNSF it helps create a downward spiral nearly 2,000 miles away.

“This has led to a significant number of eastbound trains heading for LPC being staged in sidings across the Southern Transcon waiting to arrive at and be unloaded at LPC,” BNSF told the STB. “This phenomenon has, in turn, reduced the velocity of intermodal flatcars due to their inability to be unloaded and the subsequent slowing of their return to the West Coast to handle the continued strong demand for imported cargo. It has also limited our ability to handle other traffic on the Southern Transcon as sidings, mainline segments, and terminals are congested with staged freight.”

BNSF Railway train Q-STOCHI6 09 leaves Seligman, Ariz., in its wake on Aug. 10, 2022. On the siding in town sits an international intermodal train awaiting terminal space in Chicago. (Bill Stephens)

The embargo BNSF placed on some California-bound carload traffic worked: It prevented congestion from worsening over the Fourth of July holiday week, when many crews mark off. And it helped cut in half the number of trains holding for crews.

“The decision to put the limited embargo in place was not one we took lightly,” Chief Marketing Officer Steve Bobb and Chief Operations Officer Matt Igoe wrote in an Aug. 23 letter to customers. “Still, it was a step we knew we had to take in response to significant ongoing service challenges, especially in Southern California. During the past two months, BNSF team members and contractors worked around the clock to reduce the backlogs and ensure that essential commodities flowed. Last week, we were able to grant 89% of permits requested for shipments moving into California. Moving forward, we will continue working collaboratively with individual customers to manage traffic flows and maintain fluidity.”

BNSF told customers it’s making steady progress restoring service, with manifest traffic backlogs at their lowest level since December. Terminal dwell at Barstow, where BNSF classifies traffic to and from the Los Angeles area and northern California, has fallen to 34.8 hours, down from 56 hours when the embargo began. But that’s still elevated. Railroads typically aim for cars to spend no more than 24 hours in a hump yard.

The number of trains requiring a recrew also has improved significantly, falling to 15% in California and to 12% on the Southwest Division, BNSF reported last week. Still, that meant BNSF had to tie down and recrew roughly 20 trains per day in California and 22 trains per day on the Southwest Division. This soaks up crews like a wet sponge, gobbles mainline capacity, and means BNSF can’t handle as much freight as it would like.

A crewless BNSF Railway merchandise train bound for Phoenix from Belen, N.M., sits in a siding east of Gallup, N.M., on Aug. 11, 2022. (Bill Stephens)

Service suffers

For months shippers have faced widespread delays and unpredictable transit times on the big four U.S. railroads, even as service remains at relatively normal levels on Canadian National, Canadian Pacific, and Kansas City Southern.

Overall on-time performance for the big four U.S. systems fell from a pre-pandemic average of 85% to just 67% in the last week of May 2022, according to data the railroads reported to the STB.

There hasn’t been much improvement since. Overall on-time performance stood at 72% in the week ending Aug. 19, measured by merchandise, intermodal, and bulk unit trains that arrive at their destinations within 24 hours of when originally promised.

Source: Surface Transportation Board data

The big four systems’ overall slow and unsteady progress prompted STB Chairman Martin J. Oberman to question whether the railroads would reach their service recovery goals by the end of the year.

Carload shippers say their experience mirrors the on-time performance trends, which ranges from a low of 60% at BNSF to a high of 68% at CSX. Nearly half of chemical shippers said service was worse in July compared to the fourth quarter of 2021, according to a survey by the American Chemistry Council.

Short lines also felt the pain of operational problems at their Class I connections. Says one short line leader: “Class I interchange performance is brutal.”

Even domestic intermodal service is running at historically low levels, with trains routinely arriving a day or two behind schedule, J.B. Hunt executives say. “We never saw numbers like this before the pandemic,” Darren Field, J.B. Hunt’s intermodal president, told an investor conference in August. BNSF is J.B. Hunt’s railroad partner in the west, while NS is its primary carrier in the east.

Executives from another major truckload intermodal customer, Schneider, said its intermodal service was mixed. It was “highly challenged” in the west, where Schneider’s orange containers ride both BNSF and UP, they said on the company’s July 28 earnings call. But they singled out CSX for providing excellent service in the east.

Signs of hope?

In August, BNSF, CSX, NS, and UP executives sounded optimistic. They said their railroads are slowly on the mend as more conductors graduate from training classes. Crew availability is up as summer vacation season winds down. And help has arrived in many critically short locations in the form of conductors and engineers borrowed from other areas.

Some operational data — including average train speed, recrew rates, and trains held for lack of crews — point to green shoots.

Rail executives all said that while they’re encouraged by their railroads’ progress, service is nowhere near where it needs to be. A return to 2019 operational performance, they say, likely won’t come until late this year or early next year.

The railroads say their hiring is on track to meet year-end goals.

Yet the pace of hiring is barely keeping ahead of attrition among train crews, Loop Capital analyst Rick Paterson notes. The lack of a labor agreement, threat of a strike in September, and rank-and-file union members unhappy with the Presidential Emergency Board’s wage recommendations could threaten progress the railroads have made to date.

“For some perspective on attrition, mid-July train and engine (T&E) headcount numbers were recently released and show how challenging this remains,” Paterson said in a note to clients. “BNSF saw T&E headcount fall for the third consecutive month (April 14,679, May 14,578, June 14,505, July 14,440), while the other three major U.S. railroads were able to achieve only modest sequential gains from June to July: UP 13,712 to 13,762, CSX 7,021 to 7,089, and NS 8,058 to 8,080. There’s close to equal pressure from the hiring tailwind versus attrition headwind, and the labor agreement could tip the balance either way.”

A westbound BNSF Railway stack train carrying J.B. Hunt containers departs Winslow, Ariz., on Aug. 11, 2022 as an eastbound rolls toward the terminal. (Bill Stephens)

19 thoughts on “Trouble on the Transcon

  1. @Bill Stephens RE: Train Symbols
    Not everyone reading these articles know what the various train symbols mean, eg Q-LACLPC6. Would be nice to know the origin destinations of these trains. As a former commercial pilot, I know what hundreds of the airport identifiers mean, not so much trains.

    1. Mr James, like airport codes, to a limited degree you can make a good guess about the codes. Smart guesses, if you think about where the railroad goes.

    2. Q= quality a step below a Z train which is the hottest, lac= Los Angeles lpc = logistics park Chicago 6 is the priority code 1now being highest and 9 being lowest

  2. Matt Rose 5 years ago said railroad management need to change how it does business. He’s been gone since just as covid started, and management has only gotten worse. Reregulation in support of national needs will happen within 10 years.

  3. The volume of traffic on the transcon would make scheduled call times a fairly easy trick to implement. Won’t happen as it wasn’t their idea.

  4. it’s crew issues are completely and solely due to their new availability policy. If their spin doctors want to tell the general public otherwise they can do so all they want but being right in the midst of this on this very railroad in some of the territory mentioned I can assure you people are leaving in droves, I know 6 personally since June. I also know I’d say a dozen in a certain desert terminal that are just waiting for the contract to get finalized to get back pay and their leaving. Now that sounds like a small number to the public but keep in mind that these are personal acquaintances of mine and I don’t know everyone at the particular terminal. Last I counted on the system quit or otherwise board it’s roughly 30 a day system wide. The monster they’ve created is eating them alive and they refuse to stop it for some strange reason maybe someone outside the railroad industry knows but us operating craft employees haven’t a clue anymore what they’re doing or how they’ll outdo themselves next.

  5. If the railroads, unions. and the Railroad Retirement Board would get together and not stop pension payments to retirees who resume working for a railroad some retirees might return to work. They could be requalified much more quickly than a new hire off the street.
    This would not appeal to all but some would respond.

  6. I was a director level employee in accounting, finance, and audit for a Fortune 200 Corporation. I reported to the executive suite.

    The executive team has to mange a lot of variables, i.e., customers, employees, investors, regulators, etc.

    They pay attention to Wall Street, which means many different things to many different people. However, if you believe that corporate executives spend all or even most of their time worrying about Wall Street, you are wrong! Wall Street is just one of many variables that drives their decisions.

  7. The railroads were handed a major gift in 1980 with the passage of the Staggers Act which removed burdensome government over-regulation. They took that new freedom and ran with it, and, for a while, it worked. But thanks to Wall St. and Hunter Harrison they have abused that freedom (and their workforces) to the point where the government is going to have to step back in if drastic changes are not implemented soon. The class ones had better make the necessary changes themselves rather than wait for Congress or the STB to bring the hammer down. Industry-led reforms would be preferable to bureaucratically and/or legislatively forced reforms.

    1. …and they’ll cry and whine when they do get some more regulations. Even the STB said they didn’t want to have to do it, but the RRs haven’t done a good job doing what they are supposed to do, and are doing a poor job restoring service, so what choices do they have.

      This is what happens when profits overrule everything else. They’ve had opportunities to fix their own messes & have failed; hopefully they will get some new regulations that benefit shippers, the public, and the employees. Too bad so sad for them.

    2. It’s telling that the railroads’ solution to every problem is 1-man crews. They’re hell-bent on getting that done, which has to be hampering current hiring efforts. It’s going to take the FRA or Congress to put a stop to it. Once that fantasy has been buried for good then maybe they’ll get back to full crew compliments and start running things properly. The question is how much carload traffic has been lost due to their inability to service customers? That’s one way to ease the crew shortages.

  8. It’s not our fault the truckers in Chicago won’t pick up their boxes. It’s not our fault people won’t return the chassis. It’s not our fault we didn’t hire enough people. It’s not our fault we furloughed too many people when the pandemic hit. It’s not our fault people walked away from their careers when we implemented HiViz. It’s not our fault the longshoremen can’t get the boats unloaded at the ports. It’s not our fault the weather was bad. It’s not our fault people don’t want to work here because of a sub-standard wage & working conditions in exchange for a grueling 24/7/365 on call lifestyle.

    See a pattern here? Everything would be fine, we’re doing a great job, if it wasn’t for a few factors we have absolutely no control over. Cry me a river. Those at the top are entirely to blame, yet accept no responsibility or culpability for their decisions.

  9. “BNSF, CSX, NS, and UP executives sounded optimistic. They said their railroads are slowly on the mend…” What else are these grossly overpaid prima donnas going to say? These executives are probably praying for a severe recession or a new pandemic to clear their backlogs. Clearly their management “skills” are the proximate cause for the situation.

    Decades of under-investment, abuse of the unionized workforce, the Jonestown cult of the operating ratio and asset stripping have consequences.

    Lines like the Transcon should have been electrified long ago. But Wall Street or Omaha are more interested in juicing share price and returns and simply will never make such an investment. Instead they do things like rebuilding Tier 1 locomotives, which cost as much as new, to avoid Tier 4 compliance. Things like that show their mentality.

    Those green shoots will wilt and die in the desert heat.

    1. Thing is, Gregg, that the conditions cited in the article and in your post (above) are not headed to improvement. The “abuse of the unionized workforce”, you term, continues to the present and will continue into the future.

      Everyone, raise your hand if you know any young men and women, now entering the workforce, who want to have a career in railroad T+E. I don’t see many raised arms.

    2. And if you DO know a young person expressing an interest in a railroading career, what’s the first thing you’ll say?

      “RUN AWAY!!!!! RUN AWAY!!!!!!”

      I’ve long advised people “The easiest way to end up hating railroads is to work for one.”

You must login to submit a comment